CACERCanadian Energy Regulator Act, s. 248Primary legislationIn force

Issuance

The Canadian Energy Regulator must issue permits for construction and operation of international power lines upon application, subject to the Impact Assessment Act, unless the project is designated by Governor in Council order or an alternative regulatory election applies. Applicants must provide all information specified in regulations.

Last changed 5 hours ago.

Extracted view for reading · Original for compliance evidence

Issuance

248 (1) On application, the Commission must, subject to section 8 of the Impact Assessment Act, issue a permit authorizing the construction and operation of an international power line, except in the case of a power line that is designated by order of the Governor in Council under paragraph 258(1)(a) or in respect of which an election is made under section 259. (2) The application must be accompanied by the information that under the regulations is to be furnished in connection with the application.

Source

https://laws-lois.justice.gc.ca/eng/acts/C-15.1/section-248.html

Canonical document at the regulator. Always cite this URL — not the Vantage detail page — in compliance evidence.

Related in Canada