CACERCanadian Energy Regulator Act, s. 322Primary legislationIn force

Notice of proposed acquisition or lease of lands

Pipeline companies must notify all identifiable landowners of lands required for pipeline construction or operation, providing detailed descriptions of required lands, compensation valuations, route approval procedures, and dispute resolution options. Pre-notice agreements are void, and companies are liable for all damages if they subsequently abandon acquisition or lease plans.

Last changed 5 hours ago.

Extracted view for reading · Original for compliance evidence

Notice of proposed acquisition or lease of lands

322 (1) If a company has determined the lands that may be required for the purposes of a section or part of a pipeline, the company must serve a notice on all owners of the lands, to the extent that they can be ascertained, which notice must set out or be accompanied by (a) a description of the lands of the owner that are required by the company for that section or part; (b) details of the compensation offered by the company for the lands required; (c) a detailed statement made by the company of the value of the lands required in respect of which compensation is offered; (d) a description of the procedure for approval of the detailed route of the pipeline; (e) a description of the procedure available under this Part in the event that the owner of the lands and the company are unable to agree on any matter respecting the compensation payable; and (f) any prescribed information. (2) If an agreement referred to in section 321 is entered into with an owner of lands before a notice is served on the owner under this section, that agreement is void or, in Quebec, null. (3) If a company serves a notice on an owner of lands under subsection (1) and subsequently decides not to acquire or lease all or part of the land described in the notice, it is liable to the owner for all damages suffered and reasonable costs incurred by the owner in consequence of the notice and the abandonment of the acquisition or lease of the land.

Source

https://laws-lois.justice.gc.ca/eng/acts/C-15.1/section-322.html

Canonical document at the regulator. Always cite this URL — not the Vantage detail page — in compliance evidence.

Related in Canada

CACERCanadian Energy Regulator Act, s. 90Primary legislationIn force

Compensation

Section 90 of the Canadian Energy Regulator Act clarifies that Directors, Commissioners, the Chief Executive Officer, and employees of the Canadian Energy Regulator are covered under the Government Employees Compensation Act and are considered employed in the federal public administration.

5 hours ago
CACERCanadian Energy Regulator Act, s. 145Primary legislationIn force

Public notice

The Canadian Energy Regulator must immediately notify the public when a compensation tribunal is established, including publication in the Canada Gazette detailing the tribunal's purpose and procedures for filing compensation claims.

5 hours ago
CACERCanadian Energy Regulator Act, s. 9Primary legislationIn force

Definition of document of authorization

Section 9 of the Canadian Energy Regulator Act defines 'document of authorization' as regulatory instruments issued by the CER, including certificates, permits, authorizations, licenses, and orders that establish the legal framework for energy infrastructure regulation in Canada.

5 hours ago
CACERCanadian Energy Regulator Act, s. 114Primary legislationIn force

Voluntary reporting

The Canadian Energy Regulator may establish voluntary reporting systems for alleged non-compliance with the Canadian Energy Regulator Act, subject to Governor in Council approval. Regulations may protect reporter identity, making identity-revealing information privileged and inadmissible in legal or disciplinary proceedings. Reports from protected systems cannot be used against the reporter.

5 hours ago
CACERCanadian Energy Regulator Act, s. 160Primary legislationIn force

Application

Section 160 of the Canadian Energy Regulator Act establishes a compensation claims tribunal where persons, organizations, governments, and Indigenous governing bodies may file claims for damages caused by pipeline releases from designated companies within prescribed timeframes. The Tribunal Chairperson must promptly assign claims to panels and notify all relevant parties.

5 hours ago